1 # 19th September 2023 - Diagram for proposed grant budget reallocation
2
3 *(Chart updated on 26th Sep)*
4
5 The budgets outlined below have not all been put in the bug tracker, so that
6 NLnet can confirm whether proposed changes are appropriate first.
7
8 Bug 939 - NLnet 2021 cavatools proposal 2021-08-071 - 50000
9 |
10 |- (DONE) Bug 947 - switch reference assembler to machine-readable specs - 5500
11 | RFP submitted, paid.
12 |- (DONE) Bug 958 - provide support for missing instructions in binutils - 3000
13 | RFP submitted, paid.
14 |- (DONE) Bug 976 - support missing specifiers - 1500
15 | RFP submitted, paid.
16 |- (DONE) Bug 979 - Implement C-based Power ISA decoder compiler - 5500
17 | RFP submitted.
18 |- (CANCELLED) Bug 980 - Implement C-based Power ISA pseudocode compiler - 5500
19 | *Deduct this budget from grant.*
20 |- (IN PROGRESS) Bug 981 - Support PowerPC ABI in cavatools - 4500
21 | Dmitry completed. Waiting on sign off.
22 |- (IN PROGESS) Bug 982 - Support PowerPC ABI in ISACaller - 4500
23 | (propose breakdown red 500, jacob 2500, dmitriy 1000, luke 500)
24 |- (IN PROGRESS) Bug 983 - Support PowerPC SFFS compliance - 6000
25 | |- (CONFIRMED) Bug 1169 - Add ELF and mmap support to ISACaller - 6000
26 | **Is budget for 1169 coming from 983?**
27 |- (PARTLY USED) Bug 984 - Support SVP64 in cavatools - 8000:
28 | |- (DONE) Bug 1154 - Support basic PowerPC generated assembly - 2500
29 | RFP submitted.
30 | |- Unallocated 5500 *Deduct this budget from grant.*
31 |- (CANCELLED) Bug 985 - Integrate cavatools into test API - 3000
32 | *Deduct this budget from grant.*
33 |- (IN PROGESS) Bug 987 - cavatools-related administrative activities - 3000
34 |- (DONE) Bug 997 - sorting out task schedule and MoU - 1000
35 |- (CONFIRMED) Bug 1171 - Improve budget-sync to generate HTML version of task_db/report - 2000
36 Not started, might be worth to allocate to general admin instead.
37
38 Amount for NLnet to deduct from Cavatools grant:
39 `5500 (#980) + 5500 (#984) + 3000 (985) = **14000EUR**`
40
41 ## TODO
42
43 * Andrey: Look over 982, and see what needs to be done. Wait for confirmation
44 on task 1171, but should look at budget-sync program to see how it generates
45 the individual and grant reports.
46
47 * Dmitry: Please have a think about bugs 981, the new sub-task you proposed to
48 be under 984 (assume full budget of 5500). Don't modify 981, but feel free to
49 make additional comments.
50
51 * Jacob plan out what's required for 1169, and list the necessary tasks (stick