bug 1034: making room for crfbinlog/crfternlogi/crbinlog/crternlogi
[libreriscv.git] / ghostmansd.mdwn
index 9ab54d7978f16da9e03ad20bee043af3be79a170..cf4aded4274b2deeb4b64377f05fb73ee6777f94 100644 (file)
@@ -7,26 +7,17 @@
 # Status Tracking
 
 
+## Currently working on
+
+* [Bug #980](https://bugs.libre-soc.org/show_bug.cgi?id=980):
+  Implement C\-based Power ISA pseudocode compiler
+    * this task is a MoU Milestone
+
 ## Payment not yet submitted
 
 
 ### NLnet.2022-08-051.OPF
 
-* [Bug #1054](https://bugs.libre-soc.org/show_bug.cgi?id=1054):
-  questions and feedback \(v2\) on OPF RFC ls012
-    * €500 out of total of €2500
-    * this task is part of MoU Milestone
-      [Bug #1012](https://bugs.libre-soc.org/show_bug.cgi?id=1012)
-* [Bug #1056](https://bugs.libre-soc.org/show_bug.cgi?id=1056):
-  questions and feedback \(v2\) on OPF RFC ls010
-    * €500 out of total of €3500
-    * this task is part of MoU Milestone
-      [Bug #1012](https://bugs.libre-soc.org/show_bug.cgi?id=1012)
-* [Bug #1063](https://bugs.libre-soc.org/show_bug.cgi?id=1063):
-  consider removing predicate\-result from SVP64
-    * €750 out of total of €1500
-    * this task is part of MoU Milestone
-      [Bug #1011](https://bugs.libre-soc.org/show_bug.cgi?id=1011)
 * [Bug #1089](https://bugs.libre-soc.org/show_bug.cgi?id=1089):
   feedback on OPF SVP64 RFC for "managment" instructions: ls008
     * €1250 out of total of €2500
@@ -37,13 +28,7 @@ MoU Milestone subtotals for not yet submitted payments
 
 * [Bug #1012](https://bugs.libre-soc.org/show_bug.cgi?id=1012):
   Iterative OPF ISA WG questions, feedback, and re\-submission
-    * subtotal €2250 out of total including subtasks of €22000
-
-MoU Milestone subtotals for not yet submitted payments
-
-* [Bug #1011](https://bugs.libre-soc.org/show_bug.cgi?id=1011):
-  OPF ISA WG Draft RFC Research
-    * subtotal €750 out of total including subtasks of €19000
+    * subtotal €1250 out of total including subtasks of €22000
 
 ### NLnet.2022-08-107.ongoing
 
@@ -65,11 +50,6 @@ MoU Milestone subtotals for not yet submitted payments
     * €1000 out of total of €2000
     * this task is part of MoU Milestone
       [Bug #1003](https://bugs.libre-soc.org/show_bug.cgi?id=1003)
-* [Bug #1083](https://bugs.libre-soc.org/show_bug.cgi?id=1083):
-  update to DD FFirst Mode binutils PowerDecoder
-    * €700 which is the total amount
-    * this task is part of MoU Milestone
-      [Bug #1003](https://bugs.libre-soc.org/show_bug.cgi?id=1003)
 * [Bug #1094](https://bugs.libre-soc.org/show_bug.cgi?id=1094):
   insndb instruction database visitor\-walker is needed
     * €3000 out of total of €4000
@@ -80,6 +60,15 @@ MoU Milestone subtotals for not yet submitted payments
     * €1000 which is the total amount
     * this task is part of MoU Milestone
       [Bug #1035](https://bugs.libre-soc.org/show_bug.cgi?id=1035)
+* [Bug #1150](https://bugs.libre-soc.org/show_bug.cgi?id=1150):
+  implement PO9 changeover and associated tasks
+    * €4000 out of total of €10000
+    * this task is a MoU Milestone
+* [Bug #1183](https://bugs.libre-soc.org/show_bug.cgi?id=1183):
+  add /mrr mode \(reverse mode\) to Data\-Dependent Fail\-First CR\_ops and "single looping" to DDFFirst in general
+    * €2000 out of total of €6000
+    * this task is part of MoU Milestone
+      [Bug #1027](https://bugs.libre-soc.org/show_bug.cgi?id=1027)
 
 MoU Milestone subtotals for not yet submitted payments
 
@@ -97,7 +86,63 @@ MoU Milestone subtotals for not yet submitted payments
 
 * [Bug #1003](https://bugs.libre-soc.org/show_bug.cgi?id=1003):
   instruction database continuation and binutils, SVP64
-    * subtotal €8500 out of total including subtasks of €10500
+    * subtotal €7800 out of total including subtasks of €10500
+
+MoU Milestone subtotals for not yet submitted payments
+
+* [Bug #1150](https://bugs.libre-soc.org/show_bug.cgi?id=1150):
+  implement PO9 changeover and associated tasks
+    * subtotal €4000 out of total including subtasks of €10000
+
+MoU Milestone subtotals for not yet submitted payments
+
+* [Bug #1027](https://bugs.libre-soc.org/show_bug.cgi?id=1027):
+  implement "necessary" additions to SVP64 and Scalar Power ISA
+    * subtotal €2000 out of total including subtasks of €30000
+
+## Submitted to NLNet but not yet paid
+
+
+### NLnet.2021-08-071.cavatools
+
+* [Bug #980](https://bugs.libre-soc.org/show_bug.cgi?id=980):
+  Implement C\-based Power ISA pseudocode compiler
+    * submitted on 2024-01-18
+    * €5500 which is the total amount
+    * this task is a MoU Milestone
+
+MoU Milestone subtotals for submitted but not yet paid payments
+
+* [Bug #980](https://bugs.libre-soc.org/show_bug.cgi?id=980):
+  Implement C\-based Power ISA pseudocode compiler
+    * subtotal €5500 out of total including subtasks of €5500
+
+### NLnet.2022-08-051.OPF
+
+* [Bug #1054](https://bugs.libre-soc.org/show_bug.cgi?id=1054):
+  questions and feedback \(v2\) on OPF RFC ls012
+    * submitted on 2024-01-18
+    * €500 out of total of €2500
+    * this task is part of MoU Milestone
+      [Bug #1012](https://bugs.libre-soc.org/show_bug.cgi?id=1012)
+* [Bug #1057](https://bugs.libre-soc.org/show_bug.cgi?id=1057):
+  split out all int/fp min/max ops into their own RFC ls013
+    * submitted on 2024-01-18
+    * €500 out of total of €2500
+    * this task is part of MoU Milestone
+      [Bug #1009](https://bugs.libre-soc.org/show_bug.cgi?id=1009)
+
+MoU Milestone subtotals for submitted but not yet paid payments
+
+* [Bug #1012](https://bugs.libre-soc.org/show_bug.cgi?id=1012):
+  Iterative OPF ISA WG questions, feedback, and re\-submission
+    * subtotal €500 out of total including subtasks of €22000
+
+MoU Milestone subtotals for submitted but not yet paid payments
+
+* [Bug #1009](https://bugs.libre-soc.org/show_bug.cgi?id=1009):
+  Write and submit 1st Draft External RFCs
+    * subtotal €500 out of total including subtasks of €34000
 
 ## Paid by NLNet
 
@@ -210,7 +255,7 @@ MoU Milestone subtotals for paid payments
 MoU Milestone subtotals for paid payments
 
 * [Bug #241](https://bugs.libre-soc.org/show_bug.cgi?id=241):
-  OpenPOWER SImulation is needed of standards
+  OpenPOWER Simulation is needed of standards
     * subtotal €425 out of total including subtasks of €12000
 
 MoU Milestone subtotals for paid payments
@@ -368,6 +413,24 @@ MoU Milestone subtotals for paid payments
     * paid on 2023-05-31
     * €1500 which is the total amount
     * this task is a MoU Milestone
+* [Bug #979](https://bugs.libre-soc.org/show_bug.cgi?id=979):
+  Implement C\-based Power ISA decoder compiler
+    * submitted on 2023-09-14
+    * paid on 2023-09-20
+    * €5000 out of total of €5500
+    * this task is a MoU Milestone
+* [Bug #981](https://bugs.libre-soc.org/show_bug.cgi?id=981):
+  Support PowerPC ABI in cavatools
+    * submitted on 2023-10-26
+    * paid on 2023-11-13
+    * €4500 which is the total amount
+    * this task is a MoU Milestone
+* [Bug #982](https://bugs.libre-soc.org/show_bug.cgi?id=982):
+  Support PowerPC ABI in ISACaller
+    * submitted on 2023-10-26
+    * paid on 2023-11-13
+    * €2200 out of total of €4500
+    * this task is a MoU Milestone
 * [Bug #997](https://bugs.libre-soc.org/show_bug.cgi?id=997):
   sorting out task schedule and MoU
     * submitted on 2023-03-06
@@ -375,6 +438,13 @@ MoU Milestone subtotals for paid payments
     * €500 out of total of €1000
     * this task is part of MoU Milestone
       [Bug #987](https://bugs.libre-soc.org/show_bug.cgi?id=987)
+* [Bug #1154](https://bugs.libre-soc.org/show_bug.cgi?id=1154):
+  Support basic PowerPC generated assembly
+    * submitted on 2023-09-14
+    * paid on 2023-09-20
+    * €2500 which is the total amount
+    * this task is part of MoU Milestone
+      [Bug #984](https://bugs.libre-soc.org/show_bug.cgi?id=984)
 
 MoU Milestone subtotals for paid payments
 
@@ -396,6 +466,46 @@ MoU Milestone subtotals for paid payments
 
 MoU Milestone subtotals for paid payments
 
+* [Bug #979](https://bugs.libre-soc.org/show_bug.cgi?id=979):
+  Implement C\-based Power ISA decoder compiler
+    * subtotal €5000 out of total including subtasks of €5500
+
+MoU Milestone subtotals for paid payments
+
+* [Bug #981](https://bugs.libre-soc.org/show_bug.cgi?id=981):
+  Support PowerPC ABI in cavatools
+    * subtotal €4500 out of total including subtasks of €4500
+
+MoU Milestone subtotals for paid payments
+
+* [Bug #982](https://bugs.libre-soc.org/show_bug.cgi?id=982):
+  Support PowerPC ABI in ISACaller
+    * subtotal €2200 out of total including subtasks of €4500
+
+MoU Milestone subtotals for paid payments
+
 * [Bug #987](https://bugs.libre-soc.org/show_bug.cgi?id=987):
   cavatools\-related administrative activities
     * subtotal €500 out of total including subtasks of €3000
+
+MoU Milestone subtotals for paid payments
+
+* [Bug #984](https://bugs.libre-soc.org/show_bug.cgi?id=984):
+  Support SVP64 in cavatools
+    * subtotal €2500 out of total including subtasks of €8000
+
+### NLnet.2022-08-051.OPF
+
+* [Bug #1063](https://bugs.libre-soc.org/show_bug.cgi?id=1063):
+  consider removing predicate\-result from SVP64
+    * submitted on 2023-09-14
+    * paid on 2023-09-19
+    * €750 out of total of €1500
+    * this task is part of MoU Milestone
+      [Bug #1011](https://bugs.libre-soc.org/show_bug.cgi?id=1011)
+
+MoU Milestone subtotals for paid payments
+
+* [Bug #1011](https://bugs.libre-soc.org/show_bug.cgi?id=1011):
+  OPF ISA WG Draft RFC Research
+    * subtotal €750 out of total including subtasks of €19000